 | Project ID | ST38LDBTR | | Project Name | Ledbetter Street | | Description | This project provides for reconstruction of the existing street with the addition of drainage and cul-de-sac improvements. The addition of a water line with services and a fire hydrant is also included in the scope of the project. | | Budget | $450,000 | | Project Manager | Bill Stablein | | Status | | Project Phase | | Estimated Completion | | | | | | | | |  | Construction | | June 2010 | |
| | Architect | | | Engineer | Freese & Nichols | | Construction Contractor | EBC Construction | | Project Maps | |
|
|
|