Capital Improvement Solicitations

Utilities and Environmental Services Department

Water, Wastewater, and Drainage Utility Capital Improvement Projects solicitations.

IMPORTANT CHANGES

Effective November 1, 2015, the solicitation documents for any Water, Wastewater, and Drainage Utility Capital Improvement Project may ONLY be obtained from this webpage. The City will no longer provide printed solicitations documents. Bidders are responsible for printing or obtaining prints of the solicitation documents as necessary.
Any addenda issued will be posted with the project solicitation documents below no later than two business days prior to the Bid Opening Date. Bidders may sign up to be notified when addenda is added to a project by selecting the “Get Project Addenda Notifications” button at the top of this page. The bidder is responsible for determining if any addenda have been issued.

The City may periodically update the documents herein without notice. It is the responsibility of the bidder to visit the site and check for updates.

Request for Qualifications/Proposals

TypeResponse Due DateSubmittal Due Date
No active requests at this time

Active Solicitations

Project NamePre-Bid Meeting DateBid Opening Date
No active solicitations at this time

Solicitations Pending Award

Project NameBid OpeningPending Award toProject Manager
Windy Park Channel Repair 2

Bid Form (fillable)

01/26/17A Plus Asphalt & Concrete, LLCFred Sanchez

Closed Solicitations for current fiscal year

Project NameBid OpeningAwarded toProject Manager 
Forest Creek Lift Station Rehabilitation
Notice to Bidders
Project Manual
Bid Form (fillable)
Select the “Get Project Addenda Notifications” at the top of the page to be notified of addenda.
12/21/16CRU, Ltd.Eddie Zapata
Hester’s Crossing Channel Improvements

Bid Form (fillable)

12/7/16Myers Concrete ConstructionFred Sanchez
12/7/16D&S Concrete ContractorsFred Sanchez
Lake Creek Ground Storage Tank Rehabilitation
Bid Form (fillable)
Addendum No.1 (10-11-16)
10/20/16Tank BuildersJeff Bell
 8/30/16Patin ConstructionDanny Halden
Windy Park Channel Repair
Notice to Bidders
Project Manual
1/28/16TCB Construction, Inc.Danny Halden
Sonoma 2013C Channel Erosion
12/2/15Environmental Safety Services Alysha Girard
10/15/15FlowtronexJeff Bell
8/27/15Patin ConstructionJeff Bell
7/30/15IPR South Central, LLCEddie Zapata
Purple Sage Drive Culvert Replacement
7/14/15Austin UndergroundLance Shellenberger
Lake Creek 2 and Lake Creek 3 Wastewater Line Upgrades6/25/15Austin UndergroundEddie Zapata
RTU Install and Enhancement Phase 35/7/15Trac-n-TrolJeff Bell
Dove Creek Drainage Improvements
5/5/15Patin ConstructionLance Shellenberger
AC Waterline Replacement – Phase 4 Eagles Nest Subdivision4/30/15Murphy PipelineJeff Bell
Phase – VI Reuse Water Transmission Main4/2/15Prota, Inc.Eddie Zapata
11/11/14A-Plus Asphalt and Concrete, LLC.Danny Halden
North 81 Standpipe and Barton Hill Standpipe Removal11/6/14Iseler Demolition, Inc.Eddie Zapata
Channel Erosion at Harvey Penick Drive9/17/14JKB ConstructionLance Shellenberger
Oakridge Drive and Creekview Drive Drainage Improvements9/16/14CRU, Ltd.Lance Shellenberger
County Road 112 – 24″ Waterline Extension9/4/14Bruce Flanigan ConstructionEddie Zapata