Gattis School Road Segment 6
This project is a part of the City of Round Rock’s Transportation Master Plan. It will reconstruct the existing four-lane roadway to a six-lane divided arterial from Via Sonoma Trail to Red Bud Lane. Improvements include raised median, intersection improvements, turn lanes, traffic elements and pedestrian and bicycle facilities. The project also includes improvements along Red Bud Lane at Gattis School Road. The anticipated construction cost is approximately $23 million. The project has received CAMPO funding.
Project Update: February 2026
Construction began February 2, 2026.
Project Update: January 2026
This project was required to be rebid due to significant dry utility delays and was let again on September 25, 2025. The contract was subsequently awarded to Smith Contracting on November 6, 2025.