Greenlawn Boulevard Widening

This project will add one 11-foot-wide travel lane in each direction and a separated 8-foot bicycle path along Greenlawn Boulevard from IH-35 to SH 45, a distance of approximately 1.0 mile. The existing four lane divided arterial will be widened to a six-lane enhanced section as shown in the City of Round Rock Transportation Master Plan.

Project Update: August 2026

Construction continues with utility work, basin excavation, and southbound bridge work. Traffic control estimated to remain in current configuration until October 2026 when northbound bridge and east basin improvements are anticipated.

Project Update: June 2026

Construction progressing with utility work, basin excavation, and bridge work. Traffic control estimated to remain in current configuration until September 2026.