Chisholm Trail North Widening

Widening remaining two-lane section of Chisholm Trail to match existing five-lane section.

Project Update: August 2025

The contractor is making good progress. Despite utility conflicts, the project has remained on schedule. All waterline and stormwater improvements are complete. Asphalt paving to be completed by the end of August, and the new signal will be ready September 3rd, weather permitting.

A punchlist walk is scheduled, focusing efforts on final items. Roadway illumination is progressing and is expected to be completed by the first week of September.

Completion is still tracking for this September.