- Weather permitting, waterline work on W. Main Street is slated to begin Monday, May 25. Wastewater and street excavation crews will then follow.
- Waterline crews will continue work on the west side of Mays working from north to south. A demolition and excavation crew is following immediately behind the waterline crew.
- FYI-Construction will not flip to the east side of Mays for approximately four months.