PDS Performance Measures

Target timeframes for inspections, site plan, subdivision, plat, and zoning approvals

Building Inspection Division

Inspection target: 100% of building inspections performed within one business day of request

Total bldg.
inspections
% Inspections performed within
one business day of request
January 20161246100%
February 20161303100%
March 20161378100%
April 20161317100%
May 20161382100%
June 20161609100%

.

Development Services Office (DSO)

Target: 80% of Site Development and Subdivision Improvement Permits issued after two or fewer review cycles (and one abbreviated review, or ASAP)

 Reporting period% of permits issued after  % on TargetTotal permits
(site & subdivision)
 1 review 2 reviews3+ reviews
Jan 1 – Mar 31, 201632%60%8%92%25
Apr 1 – Jun 30, 2016 33%46% 21% 79%24

.

Site/subdivision review turnaround target: 100% of reviews completed within the established review cycle period

 Reporting periodReview type & cycle length  Total reviews% on Target
 Site Development
Permit (SDP)
15 days
Small Site
Project (SSP)
10 days
Subdivision
Improvement
Permit (SIP)
15 days
Jan 1 – Mar 31, 20161141025100%
Apr 1 – Jun 30, 2016 15 36 24 100%

.

Planning Division

Plat and Zoning targets: 100% approved by P&Z within 30 days of submittal

 Reporting period# Plats
approved
% on Target# (Re)Zonings
approved
 % on Target
Jan 1 – Mar 31, 20169100%0n/a
Apr 1 – Jun 30, 2016 7100%0 n/a

.

PUD target: 90% completed and approved by P&Z within 90 days of submittal

Reporting period   #PUDs
Approved
  % on
Target
Jan 1 – Mar 31, 20164  100%
Apr 1 – Jun 30, 20160n/a

.

 