- Excavation will begin on W. Main in approximately two weeks.
- Crews will be working on storm sewers, curbs and concrete driveways along Mays for the next several weeks.
- Utility work is being finalized on W. Liberty and it should be reopened in approximately two weeks. It will be closed again in 3-4 months when curb, gutter and sidewalk work begins.
- Curbs will be installed at Bagdad and Mays the latter part of this week. The intersection will be closed for 2-3 days.
- Crews will be working on an electric duct bank at Round Rock Ave. and Brown for 3-4 days next week. The work will be done between 9am-4pm every day and Brown will remain accessible from the south.
June 24 Update
RECENT NEWS
Round Rock again listed among best places to live in U.S.
May 2, 2024
11:03 am
City Council considers changes to non-resident memberships at Round Rock Public Library
April 25, 2024
7:17 pm
City of Round Rock’s AAA bond rating reaffirmed by S&P Global
April 25, 2024
7:09 pm
Round Rock and Dell Technologies extend original agreement through 2099
April 25, 2024
6:45 pm
SHARE
SUBSCRIBE TO NEWSFLASH
Round Rock’s digital newsletter providing residents news, events and general information regarding city government.