July 14 Update

  • Excavation is slated to begin on W. Main on Wednesday or Thursday of this week.
  • W. Liberty will be re-opened by the end of this week. It will be closed again in 3-4 months when curb, gutter and sidewalk work begins.
  • Crews will continue work on wastewater, curbs and concrete driveways along Mays for the next several weeks.

 

 

 