- Crews will continue work on the north side of W. Main for the next 1.5-2 weeks. After that time, they will mimic the work on the south side of the same strip of W. Main. Â After excavation, black base will be laid and curbs, sidewalks and drives will be installed. It is anticipated that this work will be completed in approximately two months.
- Crews will complete the last driveway along the west side of Mays by the end of the week.