- Crews will continue work on the north side of W. Main for the next 1.5-2 weeks. After that time, they will mimic the work on the south side of the same strip of W. Main. After excavation, black base will be laid and curbs, sidewalks and drives will be installed. It is anticipated that this work will be completed in approximately two months.
- Crews will complete the last driveway along the west side of Mays by the end of the week.
July 29 Update
RECENT NEWS
City of Round Rock’s AAA bond rating reaffirmed by S&P Global
April 25, 2024
7:09 pm
Round Rock and Dell Technologies extend original agreement through 2099
April 25, 2024
6:45 pm
Round Rock proclaims May as Historic Preservation Month
April 25, 2024
6:19 pm
Early voting begins for May 4 election
April 22, 2024
1:54 pm
SHARE
SUBSCRIBE TO NEWSFLASH
Round Rock’s digital newsletter providing residents news, events and general information regarding city government.