If your address was not serviced during this weekend’s Spring Cleanup event, please leave your bulk items at the curb for pickup to resume Monday. Saturday’s pickup experienced delays due to high volume.

June 10 Update - City of Round Rock

June 10 Update

  • Waterline work on W. Main has been completed and wastewater should be completed by the end of the week. Street excavation crews will follow immediately behind.
  • Waterline crews will continue work on the west side of Mays working from north to south. Irrigation lines and manholes are also being set this week.
  • Utility work continues on Liberty. As soon as the manholes needed for the utilities are set over the next few weeks, Liberty will be reopened to Mays until curb, gutter and sidewalk work commences sometime this fall.
Scroll to Top