  • Waterline work on W. Main is underway and should be completed by the end of the week. Wastewater and street excavation crews will follow immediately behind.
  • Waterline crews will continue work on the west side of Mays working from north to south. A demolition and excavation crew is following immediately behind the waterline crew.
  • Utility work continues on Liberty this week. As soon as the manholes needed for the utilities are set over the next few weeks, Liberty will be reopened to Mays.

 