June 3 Update

  • Waterline work on W. Main is underway and should be completed by the end of the week. Wastewater and street excavation crews will follow immediately behind.
  • Waterline crews will continue work on the west side of Mays working from north to south. A demolition and excavation crew is following immediately behind the waterline crew.
  • Utility work continues on Liberty this week. As soon as the manholes needed for the utilities are set over the next few weeks, Liberty will be reopened to Mays.

 

Share thisShare on Facebook
Facebook
Tweet about this on Twitter
Twitter