In 2019, the City of Round Rock put in place funding strategies to accelerate transportation improvements over the next five years – and beyond. The intent is to step up the pace of implementation of the $1.2 billion Transportation Master Plan approved in October 2017.
The City Council approved Roadway Impact Fees in March 2019, which will be paid by developers to cover some of the costs of expanding our transportation network necessitated by their projects. In April 2019, the City issued $30 million in certificates of obligation to begin work sooner rather than later on major roadway improvements such as widening Gattis School Road and University Boulevard.
The City has a target of investing a minimum of $240 million over the next five years to improve roadway capacity and connectivity in a program we’re calling Driving Progress. To reach that total, the City plans to issue additional COs over the next four years.
Other funding sources include our half-cent, Type B sales tax revenues, state and federal funds like those received through the Capital Area Metropolitan Planning Organization (CAMPO); and partnerships with private developers. Funding for Round Rock projects is also expected via the general obligation bonds approved by Williamson County voters in November.
Here are some of the projects expected to break ground in 2020:
- University Boulevard widening from the IH-35 frontage road to Sunrise Boulevard.
- University Boulevard widening from A.W. Grimes Boulevard to SH 130.
- Gattis School Road widening from Via Sonoma Trail to Red Bud Lane.
- Logan Street extension from Greenlawn Boulevard to A.W. Grimes Boulevard.
- Kenney Fort Boulevard extension from Old Settlers Boulevard to Joe DiMaggio Boulevard (known as Segment 4).
- Kenney Fort Boulevard extension from Forest Creek Drive to SH 45 frontage road (known as Segments 2, 3).
Other projects in the Driving Progress program include:
- Gattis School Road widening from .25 miles west of A.W. Grimes to .2 miles east of Double Creek Drive (known as Segment 3).
- Wyoming Springs extension from Brightwater Boulevard/Creekbend Boulevard to FM 3406/Old Settler’s Boulevard.
- Red Bud Lane North widening from Wal-Mart at U.S. 79 to County Road 117.
- Red Bud Lane South widening from Evergreen Drive to Gattis School Road.
Partner in Progress
These lists don’t include the significant work being done by the Texas Department of Transportation in Round Rock, most notably the widening of RM 620 and improvements to IH 35.